"How long will the shop take?" is one of the most common questions before a project. The honest answer has two parts: how long we need for the build and how long the project runs in the calendar overall. The difference comes from things outside the agency: content, logins, data, feedback and approvals. That's why we name both times and the prerequisites for them. That way a build time isn't confused with a fixed launch date.
The case
A client calculates with the stated build time and plans their launch around it. Then product images are still missing, access to inventory management only comes after a week, and a feedback round takes longer than expected. The shop wasn't built any slower, but the calendar kept running. Without clarification upfront, this quickly creates frustration on both sides.
What determines the time
| Lies with us | Lies with the client or third parties |
|---|---|
| Design and building the templates | Copy, images and product data |
| Setting up apps and settings | Access to shop, domain and systems |
| Data migration | Feedback and approvals |
| Tests and corrections | Setup at the app or ERP provider |
How we build the schedule
- State build time and project duration separately. Both numbers belong in the offer.
- Name the prerequisites. What has to be available when for the plan to hold?
- Plan in feedback rounds. With a clear timeframe for responses.
- Make dependencies on third parties visible. App and ERP providers have their own schedules.
- Talk early about delays. Better a week before than on the planned launch day.
What you can take away
- Ask for both times. How long is the build, and how long does the project run?
- Feedback loops determine the calendar more than individual pages. Plan time for your own responses.
- Prepare content early. Missing images and copy are the most common reason for delays.
- A clear schedule protects both sides. People who know the prerequisites can meet them.